If you manufacture products in China, a good rule is to place orders at least 90 to 120 days before Chinese New Year.
That does not mean every factory needs four months to produce an order. The extra time protects you against the production bottleneck that builds before the holiday, including supplier capacity constraints, material delays, quality inspections and limited freight space.
For custom products, new tooling or more complicated manufacturing, planning 120 to 150 days ahead may be safer.
How Early Should You Place Orders Before Chinese New Year?
For most established products and repeat orders, the safest window is around 90 to 120 days before Chinese New Year.
Some may cause only a short interruption. Others can affect factory output and logistics for considerably longer than the official holiday dates.
A practical planning timeline looks like this:
| Time Before Chinese New Year | Recommended Action |
|---|---|
| 120+ days | Finalise specifications, samples, packaging and supplier capacity. |
| 90–120 days | Place the production order and confirm the manufacturing schedule. |
| 60–90 days | Monitor production and prepare quality inspections. |
| 45–60 days | Complete inspections and confirm freight bookings. |
| 30–45 days | Avoid relying on new production unless your supplier has confirmed capacity. |
| Final 2–3 weeks | Focus on shipping completed goods rather than starting new production. |
Companies ordering custom-made products should allow additional time for sampling, tooling, material procurement and production approval.
Our product sourcing service helps businesses coordinate these stages with suppliers before production capacity becomes restricted.
When Do Chinese Factories Start Slowing Down?
Factories do not suddenly stop operating on the first day of Chinese New Year.
The slowdown often begins several weeks before the official holiday.
Many factories rely heavily on migrant workers who travel long distances to return home for the holiday. Some workers leave early, while component suppliers, packaging factories and subcontractors may also start reducing operations.
This creates several potential problems:
- Production lines may operate with fewer workers.
- Raw materials can become harder to source.
- Quality control teams become busier.
- Factories may prioritise larger or long-standing customers.
- Suppliers may rush production to complete orders before closing.
This is why an order scheduled to finish shortly before Chinese New Year carries more risk than one completed several weeks earlier.
If you are new to managing Chinese suppliers, our guide on how to source products from China step by step explains the wider sourcing and production process.
How Long Do Chinese New Year Factory Closures Last?
The official public holiday does not reflect the full manufacturing disruption.
Many factories may stop production for around one to two weeks, but the practical impact can last considerably longer.
Workers often begin leaving before the holiday and return gradually afterwards. Factories may then need another one to three weeks to rebuild their workforce and return production lines to normal output.
As a result, importers should plan for a broader disruption window rather than simply counting the official holiday dates.
The exact shutdown period varies by:
- Factory location
- Industry
- Workforce
- Supplier network
- Production complexity
- Availability of raw materials
Always ask your supplier for their planned production cut-off and reopening schedule instead of assuming every factory follows the same calendar.
What Happens to Freight Before Chinese New Year?
Production is only half of the problem.
Freight capacity also becomes increasingly competitive as exporters try to move finished goods before factories close.
Sea freight bookings can become harder to secure and rates may rise as demand increases. Containers may also be rolled onto later sailings if vessels reach capacity.
For this reason, businesses should avoid treating the factory completion date as the final deadline.
Allow enough time for:
- Final production
- Quality inspection
- Rework if defects are discovered
- Packaging
- Inland transportation
- Export documentation
- Freight booking
- Port handling
Our freight forwarding team can coordinate production completion with shipping schedules so goods do not become stranded during the pre-holiday rush.
Is 90 Days Before Chinese New Year Always Enough?
No.
The 90-day guideline works best for straightforward products where specifications, samples and suppliers are already confirmed.
You should consider ordering earlier when your project involves:
- New product development
- Custom tooling or moulds
- Bespoke packaging
- Multiple factories
- Complex quality inspections
- Large production volumes
- New suppliers
- Components with long material lead times
Waiting until the last possible production slot creates very little room for mistakes.
A failed inspection, production delay or unavailable shipping container can quickly push an order beyond the Chinese New Year shutdown.
Plan Your Pre-CNY Production Before Capacity Tightens
Chinese New Year disruption is predictable. Poor planning around it is avoidable.
For most businesses, beginning production planning 90 to 120 days before the holiday provides a reasonable buffer. Complex or highly customised orders should begin even earlier.
Connected Sourcing can help coordinate suppliers, production, inspections and freight as one process, reducing the risk of your order being caught in the Chinese New Year manufacturing slowdown.
Planning an upcoming production run?
Explore our Product Sourcing service and start planning your pre-CNY production before factory capacity becomes limited.